Based on technical , schedule, and management considerations, NASA did not consider conducting a competitive procurement for a propulsion module. Rather, NASA modified its existing contract with the space station prime contractor, Boeing Corporation, to obtain this capability without competition. The modification of NASA's contract with Boeing was proper. The Changes clause of the prime contract allowed NASA to modify the contract to add additional requirements, provided they were "within the scope" of the contract. NASA reasonably concluded that the propulsion module requirement was within the scope of Boeing's prime contract, which assigned Boeing the responsibility to design, develop, and deliver the U.S. segment of the space station.