The administration’s proposed FY2003 defense budget request S424.7 million
in advance procurement funding for CBNX-1, and aircraft carrier that the
Navy plans to procure in FY2007 and commission in 2014, CVNX-1 was
previously planned for procurement in FY2006 and commissioning in 2013. The
Navy estimates that the decision to procure CVNX-1 un FY2007 rather than
FY2006 increased the ship’s procurement cost by $403 million. Some
supporters of CVNX-1 in Congress want to restore the ship’s original 2013
commissioning date and are proposing th add $229 million to the FY2003
budget request to support this goal.
The Navy estimates that CVNX-1 will cost $2.54 billion to develop and $7.48
billion to procure, bringing its total acquisition (development plus
procurement) cost to $10.02 billion. The Navy estimate that CVNX-2 (a
carrier planned for procurement around FY2011) will cost $1.29 billion to
develop and $7.49 billion to procure, for a total acquisition cost of $8.78
billion. This report will be updated as events warrant.
-